1992/04/23 – Preliminary Assessment / Visual Site Inspections (PA/VSI)PA/VSI to identify and assess the existence and likelihood of releases from areas of concern.Download
1992/08/19 – Air Use PermitMichigan DEQ Air Use Permit application for plastic injection molding facility.Download
1996/04/04 – MDEQ Letter – UST Release at CMI-Tech CenterMDEQ letter confirming notification of UST release reported on March 29, 1996.Download
1996/04/15 – Confirmed Release Report – CMI-Tech CenterMDEQ report from gasoline UST release reported on March 29, 1996.Download
1996/07/02 – Leaking UST – Initial Assessment ReportInitial assessment report for the UST release discovered on March 28, 1996.Download
1997/04/03 – Closure Assessment ReportClosure report for the UST release discovered on March 28, 1996.Download
1998/02/04 – MDEQ Letter – Audit of Corrective ActionsMDEQ audit of corrective actions for the UST release reported on March 28, 1996.Download
2005/05/04 – PCE Completion SummaryMDEQ air permit compliance investigation report.Download
2008/05/30 – MDEQ Letter – USTs at CMI Tech CenterMDEQ letter requesting proof of financial responsibility for USTs.Download
2008/08/13 – Suspected Release Report – CMI-Tech CenterMDEQ report from gasoline and diesel UST releases reported on August 12, 2008.Download
2008/08/27 – ECT (Environmental Consulting) Letter to MDEQ – Underground Storage Tank System Site Assessment ReportAssessment report for removal of two USTs on July 8, 2008.Download
2008/08/29 – UST Site Assessment ReportMDEQ closure form for two USTs removed on July 28, 2008.Download
2008/10/29 – MDEQ MemoMDEQ memo regarding closure following UST removals.Download
2013/04/15 – Acknowledgement of Receipt of BEAMDEQ letter of receipt of December 5, 2012 Baseline Environmental Assessment.Download
2015/02/25 – LARA MDEQ EmailLicensing and Regulatory Affairs (LARA) request to close site evaluations to MDEQ.Download
2015/12/17 – LARA Letter to Hayes LemmerzLetter noting cancellation of suspected release entered on August 12, 2008.Download
2016/06/17 – Baseline Environmental Assessment – PM EnvironmentalJune 17, 2016 Baseline Environmental Assessment of the Former Ethyl Corp Property.Download
2016/08/29 – Acknowledgement of Receipt of BEAMDEQ letter of receipt of June 17, 2016 Baseline Environmental Assessment.Download
2019/06/18 – Acknowledgement of Receipt of BEAMDEQ letter of receipt of May 24, 2019 Baseline Environmental Assessment.Download
2021/09/21 – RCRA Corrective Actions – Description of Current Conditions and Interim Measures Report2021 ATC RCRA Corrective Action Report submitted to MDEQ.Download
2022/02/17 – RCRA Corrective Action – Facility Investigation Workplan2022 Atlas RCRA Corrective Action Report Submitted to MDEQ.Download
2022/04/19 – RCRA Interim Work Plan Investigation Report – Eastern Site Boundary2022 Atlas RCRA Corrective Action Report Submitted to MDEQ.Download
2022/06/23 – Comment Letter – RCRA Interim Work Plan Investigation Report – Eastern Site BoundaryMichigan EGLE comments to April 19, 2022 Interim Work Plan Investigation Report.Download
2022/07/07 – Comment Letter – RCRA Corrective Action Facility Investigation Work PlanMichigan EGLE comments to February 7, 2022 Corrective Action Facility Investigation Workplan Report.Download
2022/08/16 – Response to EGLE Comments and Addendum to the RCRA Interim Work Plan Investigation Report – Eastern Site BoundaryTRC response to EGLE comments addendum to April 29, 2022, RCRA Interim Workplan Report.Download
2022/09/07 – Revised RCRA Corrective Action Facility Investigation Work Plan Report2022 TRC revised RCRA Correction Action Facility Workplan Report.Download
2022/10/13 – Conditional Approval – RCRA Corrective Action Facility Investigation Work PlanEGLE 2022 EGLE conditional approval and response to comments.Download
2022/10/17 – Work Plan Conditional Approval – Response to Comments and Addendum to the RCRA Interim Work Plan Investigation Report – Eastern Site Boundary2022 EGLE conditional approval and response to comments.Download
2023/04/03 – Continued Eastern Boundary Investigation Report2023 TRC Investigation Report submitted to EGLE.Download
2023/06/23 – Conditional Approval – Continued Eastern Boundary Investigation Report2023 EGLE conditional approval and response to comments.Download
2023/07/07 – Southern Area Investigation Report2023 TRC Southern Area Investigation Report submitted to EGLE.Download